Múzeum utca 11

The basement base plate is being made continuously on the construction site. As well as the lowering of the foundation level, our specialists are working on the constructions of the church. Demolition work will take another 2-3 weeks.


The following workflows are currently underway in the project: The basement base plate is made continuously As well as the lowering of the foundation level, the church structures are also permanent. About 1,500 m3 of material remained from the demolition work. In addition to the demolition work, the static condition of the building will be confirmed and repaired at the same time.